Sunday, 8 September 2013

Day 170 - All Coming Together

We met with our SS on Friday to go through the house.
 
The house was abuzz with painters and tilers busy working on the house. Whilst we were there we also found time to get a quote for the window furnishings. I wasn't too sure what we were going to go with - so much to choose from. Curtains, roller blinds, plantation shutters!
 
We finally settled on the idea of getting a variety of furnishings for the windows which will compliment each room.  I am still going through the quotation process so I'll give you more details on my choice and who I chose when this is finalised.  I am looking at getting a few quotes (I figure I have the time so no need to rush).
 
A combination of double roller blinds with pelmets, plantation shutters and curtains is where I am headed.  I have no idea of colours as yet.  I was hoping to make this decision after the floorboards are installed.  This should help us make a more informed decision.
 
Overall the house is coming together.  The painting has made a huge difference to the feel of the house. Our SS is still reluctant to give us an estimated handover date.  We are hoping for December.  It would be great to get into the house before Christmas.  I would also like to start locking away a landscaper so that our Alfresco area and front yard can be worked on during the Summer.

After all this time we now have to pull up our sleeves and start getting organised. Below are some photos we took on Friday of the house so far.  We were very excited to see the tiling, or what has been done so far.


Looking into the living room - love those picture windows. Waiting for the fireplace to be installed on the wall. Paint colour is Grand Piano Half - Ceiling and Cornice is in Natural White.


Living room - cabinetry still be finished - as mentioned before waiting patiently for the fireplace.

 
Master bedroom


Ensuite - we have tiles - porcelain to be exact!



Monday, 22 July 2013

Day 122 - Plaster it Up

It has been a busy week at the house.

For some time we have been waiting patiently to see more work at the house and in the past week we have seen the blueboard finished ready for render and the front two pillars (Nuvo Facade) being preped for render as well.

We also had the plasterer come through the house. 

We had a quick look on the weekend and were really excited to see the plaster throughout the house. 

We can now see the house come to life.

Our Site Supervisor told us that once the plasterers finish up the cornices will be installed and then hopefully the staircase and the kitchen will be installed.

I am yet to take a look upstairs so I am looking forward to seeing the staircase! 

Below are some pics of the house with plastering....

Hallway Entry - Theatre room on the left
 
 
 
Dining Room and Family Room - photo taken from the kitchen


Saturday, 22 June 2013

Day 92 - Where is the Love?

Day 92 and we are still no closer to lock up. The bricklayers have done as much as they can (so I am told), but they still haven't finished off the garage.

Our Site Supervisor has told us that they need to finish off the piping/drainage on the side of the garage and until they do this the garage can't be finished.  This is holding up everything else. Without the garage up they can't start putting the blue board up and so the list goes on. Fingers crossed this gets sorted this week.

Communication at Metricon headquarters has also ceased...We should be getting weekly updates from our Site Supervisor but that doesn't seem to be happening - unless we contact him.  This is getting a little frustrating considering we have heaps of questions and queries that we want answers on. In saying that our Site Supervisor has been great so far....when we get a chance to chat with him. In fact I was lucky enough to speak to him on Friday so I believe we will be catching up this week. Finally.

Such a huge volume builder like Metricon I guess it is to be expected that our Site Supervisor has more than one home to look after, keeping him very busy.  That being said this one home is our home and therefore I expect a lot from Metricon.  Not only in the final product but also in the service along the way.

I am sure many of you will agree with me that signing a Building Contract is a big step.  For us it was years in the making, so I guess when it comes to expecting a detailed phone call once a week with answers to our questions - it's not a lot to ask or expect.  I also know that there will be some weeks that go by which there is nothing major to update us on, however we have a list of 17+ queries sitting with Metricon at the moment we're waiting to get answers to.

This is not a personal attack on our Site Supervisor at all.  Like I said he is doing the best he can and we appreciate his honesty and help along the way.  This is more of an understanding that I think Metricon need to work at.

If the Site Supervisor is too busy then we need someone else to contact us and let us know where the build is at.  Either way we should be getting this phone call.

It would be great to hear if anyone else has had the same types of issues a long the way.




Saturday, 25 May 2013

Day 63 - First Look of Upstairs!!

It has been some time since my last post. 

The house is still being bricked up and so I wanted to give it some time before I posted more photos... 

We went passed the house today only to find the "brickies" working!  On a Saturday...we were impressed!  Looks like Metricon are running on a strict timeline and these guys need to meet it!

It is funny though...there are a few houses being built around where we live and most of them started construction when we did.  None of the houses have roofs, most are still having the frames put up.  I have to say Metricon have been very efficient in getting things organised.  That is definetly a big plus.

There has also been some development inside the house. The internal cavity doors were delivered and installed downstairs which was exciting. They still need to be painted though...so everything is still very raw.

We also got a glimpse of the work that is being done upstairs....




Main Bedroom - looking out to the balcony
 
Main Bathroom upstairs


Main Bedroom - looking into Ensuite

 
Brickwork on the house





Sunday, 21 April 2013

Day 30 - And then there were frames...

I have been meaning to post these pics for the past couple of days....we now have the ground floor frames up...so exciting!

It seems like everything has happened pretty quickly but I am guessing with Anzac Day this week the Metricon team will want to get as much work done as possible....so they can have their 3 day week....(I am guessing tradies will have Friday off as well).

Clive, our Site Manager, has mentioned to us that the 2nd floor frames should go up this week so there will be more photos to come....

Below are a couple of photos we took yesterday in the beautiful Autumn sun.....